DD Form 1423 (CDRL) Explained: How to Read a Contract Data Requirements List Before You Quote
Short answer: DD Form 1423 is the Contract Data Requirements List, or CDRL. It is the form a Department of Defense buying office uses to list every piece of data a contract requires you to deliver, such as a certificate of conformance, a first article test report or an inspection report. DFARS 215.470 tells DoD contracting officers to include a DD Form 1423 in the solicitation whenever data must be delivered under the contract. Once you win, each CDRL becomes a contractual delivery, just like the parts. FedOpp is research software that helps small manufacturers find, read and research DLA and DoD solicitations before they quote on the official portals.
By FedOpp. Facts current as of November 18, 2026. FedOpp is an independent research tool and is not affiliated with SAM.gov, the Department of War (Department of Defense), the Defense Logistics Agency or any government agency. This post is general information, not legal advice.
What is a CDRL?
A CDRL (Contract Data Requirements List) is "an authorized list of data requirements for a specific procurement that forms part of a contract in conjunction with applicable DIDs," according to War University's Acquipedia reference on CDRLs and DIDs. The same entry says DD Form 1423 "is used for identifying potential data requirements in a solicitation, and becomes an exhibit with data deliverable requirements in a contract."
War University's CDRL Step by Step course puts it more bluntly: the completed DD 1423 "requires the contractor to formally deliver the data (contractual obligation) to the Government." CDRLs are usually found in the contract under Section J, Exhibits.
"Data" here is broad. The course lists test data, computer software, design details, progress reports, technical data, and financial or management reports.
What is a DID, and how does it connect to the CDRL?
A Data Item Description (DID) is the document that defines what goes into the data item. Acquipedia calls it "a standardization document that defines the data required of a contractor," including "the data content, format, and intended use."
Think of it this way:
- The CDRL says what to deliver, when, how often, to whom and in how many copies.
- The DID says what that deliverable must contain and how it must look.
DID numbers start with "DI-". For example, one Navy solicitation for an epoxy adhesive (N00104-23-Q-NE65, July 2023) listed CDRL item A001 as "CERTIFICATION/DATA REPORT" under DID DI-MISC-80678. You can look up DIDs in DLA's ASSIST database, which Acquipedia names as the place to search them.
Where do CDRLs show up in DLA and DoD solicitations?
DFARS 215.470(b) is the rule: "When data are required to be delivered under a contract, include DD Form 1423, Contract Data Requirements List, in the solicitation." That applies across DoD buying offices, including DLA and the Army offices that post buys in PIEE.
In practice, look for these clues in the solicitation, its attachments and the technical data package:
- The words "DD Form 1423," "CDRL" or "Exhibit A"
- Data item numbers that start with "A0" (A001, A002) and DID numbers that start with "DI-"
- Statement of work or quality paragraphs that say "in accordance with the Contract Data Requirements List"
The Navy solicitation above is a good example. Its quality section required a material safety data sheet, a certification of conformance, a first article test report and a production lot test report, each "in accordance with the Contract Data Requirements List (DD Form 1423)." The first article report "shall be approved prior to production."
Our PIEE Solicitation Module guide flags the same trap for Army part buys: the CDRLs often sit in the attachments, and skipping them is a common mistake.
How to read DD Form 1423, block by block
The block meanings below come from the DD Form 1423 instructions printed in that Navy solicitation (section 6.3). Always check the instructions in your own solicitation, because buying offices can add their own notes.
| Block | What it tells you | What to check |
|---|---|---|
| 1 | Data item number. The Navy instructions call it the Exhibit Line Item Number (ELIN); the example used A001 | Match it to every place the solicitation mentions that item |
| 2 and 3 | Title and subtitle of the data item | Quick sense of the deliverable |
| 4 | The DID number (or a technical manual requirement number) | Pull the DID from ASSIST and read it before you price |
| 5 | Contract reference: the section and paragraph that sets the requirement | Read that paragraph too |
| 6 | Requiring office: who approves or disapproves the data | Who you will be dealing with |
| 7 | DD 250 code: where inspection and acceptance of the data happen | Whether a government inspector must see it first |
| 8 | Approval code. "A" means a draft must be approved before the final | Build review time into your schedule |
| 9 | Distribution statement code | How the government may share the data |
| 10 | Frequency, such as ASREQ (as required), ONE/R (one time with revisions), MTHLY or QRTLY | How many times you will deliver it |
| 11 | As-of date. In the Navy instructions: the date a one-time item must reach the requiring office, or for repeat items, the number of days after each period | Whether you can actually hit it |
| 12 and 13 | Date of first submission and of later submissions | A date or a code such as DAC (days after contract date) or ASREQ, explained in Block 16 |
| 14 and 15 | Distribution: addressees and number of draft and final copies, and the total | Where every copy goes |
| 16 | Remarks. The only place the DID can be tailored, and only by deleting requirements | Read this block line by line |
| 17 | Price group (I to IV) | Filled in by the offeror |
| 18 | Estimated total price for the data item | Filled in by the offeror; "N/C" (no charge) is allowed |
Two blocks deserve extra attention:
- Block 10 and Block 16 work together. The Navy instructions say the frequency codes need "further explanation in Block 16 to provide the contractor with guidance necessary to accurately price the deliverable data item." If Block 10 says ASREQ, Block 16 should say what triggers it.
- Block 16 is where the real instructions live. In the Navy example, the remarks told the supplier to pack one approved copy inside each shipping container and send another copy with the shipping paperwork. The Navy instructions say Block 16 also spells out approval turnaround times when a draft is required, and can set the delivery medium.
How do you price CDRL data items?
DFARS 215.470(a) says "DoD requires estimates of the prices of data" so it can weigh the value of each data item. The related DFARS guidance (PGI 215.470) explains that the form asks you to state what portion of your total price is for producing or developing the listed data, "not to the sale of rights in the data."
The Navy instructions define four price groups for Block 17:
- Group I: data you create only because the government asked for it.
- Group II: data you need anyway, but must rework to meet government requirements.
- Group III: data you create for your own use that needs no real change; only reproduction, handling and delivery are priced.
- Group IV: data you already have from your commercial business. Usually coded "no charge."
Some solicitations list data as "Not Separately Priced." In the Navy example, the data exhibit line carried a unit price of 0, marked "Not Separately Priced." Nobody pays you a separate line for those certificates and reports, so build the hours into your item price. Our guide to pricing DLA bids from procurement history covers the rest of the quote.
DFARS 215.470(c) adds one more rule: the contract should not ask for data you already delivered, or must deliver, under another contract. If the government wants a duplicate anyway, the price covers duplication, not preparation.
What does a small supplier actually have to deliver?
Exactly what each CDRL says, in the form its DID describes, on the dates in Blocks 12 and 13, to the addressees in Block 14. In the Navy example, the CDRL-driven deliverables were:
- A certificate of conformance
- A first article test or inspection report, approved before production starts
- Production lot test or inspection reports
- A material safety data sheet (the item was an adhesive)
Your list will depend on the part and the buying office, so read every CDRL in your own solicitation.
If the buy calls for traceability documents or product verification testing, see RQ048 on DIBBS. If the buy has a first article requirement, read our explainer on first article testing and how to price it next.
A 6-step CDRL check before you quote
- Search the solicitation and every attachment for "1423," "CDRL" and "DI-".
- List each data item number (A001, A002 and so on) with its title.
- Pull each DID in Block 4 from ASSIST and read the content and format rules.
- Read Block 16 for each item. Note tailoring, delivery medium and approval turnaround.
- Put the due dates from Blocks 12 and 13 on your production schedule, including any approval loop from Block 8.
- Price the labor and inspection time, either in Block 18 or inside your part price if the data is not separately priced.
FedOpp's Contract Reader turns an uploaded solicitation PDF into a plain-English brief of scope, deadlines, packaging and risk flags. Use it to get oriented, then check every CDRL against the official file. For a broader walk-through, see how to use AI to read a solicitation and how to read a DIBBS RFQ.
FAQ
What is DD Form 1423?
DD Form 1423 is the Contract Data Requirements List (CDRL). DoD buying offices use it to list each data item a contract requires, such as test reports or certificates, along with the governing Data Item Description, due dates, frequency and distribution. DFARS 215.470 requires it in the solicitation whenever data must be delivered under the contract. After award, it becomes a contract exhibit.
What does CDRL stand for?
CDRL stands for Contract Data Requirements List. It is the list of data deliverables on a defense contract, recorded on one or more DD Form 1423s. Each line names the deliverable, cites the Data Item Description (DID) that defines its content and format, and sets the delivery schedule and addressees. Delivering CDRL items is a contractual obligation, not a courtesy.
What is the difference between a CDRL and a DID?
The CDRL tells you what to deliver, when, how often and to whom. The Data Item Description (DID), cited in Block 4, defines what the deliverable must contain and its format. War University's Acquipedia describes the DID as the document that "defines the data content, format, and intended use." You need both to price and deliver the item correctly.
Where is the CDRL in a solicitation?
Look in the solicitation attachments, the technical data package and the contract exhibits (Section J in many contracts). Search for "DD Form 1423," "CDRL," "Exhibit A," item numbers like A001, and DID numbers that start with "DI-." Statement of work and quality paragraphs often point to the CDRL with the phrase "in accordance with the Contract Data Requirements List."
Do I have to price CDRL items separately?
It depends on the solicitation. When Blocks 17 and 18 ask for a price group and an estimated price, you enter them. When the data line is marked "Not Separately Priced," there is no separate payment for the data, so build that cost into your item price. Either way, count the labor, inspection and paperwork time before you quote, because the data is due just like the parts.
Related reading: Which DIBBS RFQs Should You Bid On? and WAWF Invoice in PIEE: How to Bill a DLA Order
This post is general information as of November 18, 2026, not legal or contracting advice. Always follow the instructions in your own solicitation. Sources: DFARS 215.470; DFARS PGI 215.470; DFARS 227.7103-2; War University Acquipedia, "Product Support: Contract Data Requirements List (CDRL) and Data Item Descriptions (DID)"; War University CDRL Step by Step, Step 7; NAVSUP WSS solicitation N00104-23-Q-NE65 (July 7, 2023), section 6.3 and CDRL A001.